Full apartment renovation in Chișinău, in older blocks

Full apartment renovation in Chișinău for flats on the resale market, such as Soviet-era series 143 blocks. We strip out everything old, replace the wiring and pipes, level walls, ceilings and floors, then do the finishing.

Leave a request

The data is processed in line with the privacy policy.

Old flat after demolition, with exposed brick walls and rubble on the floor

When a flat needs a full renovation

When the wiring and pipes date from the block's construction, walls are crooked, or you want to move a partition. Here a cosmetic renovation isn't enough: replacing the pipes later means breaking freshly painted walls. Of all the ways to do an apartment renovation in an old block, this one replaces everything at once.

Replaced

  • the wiring, from the consumer unit to every socket
  • water and drain pipes, up to the building's riser
  • loose plaster and moved partitions
  • the screed, for a level floor
  • finishing in every room, bathroom and kitchen

Stays as it is

  • the building's load-bearing walls
  • double-glazed windows, if they're good
  • the shared water and drain risers, which belong to the building

What we do in a full renovation

The estimate starts with demolition on separate lines, so you see what it costs on its own. Then services, levelling and finishing.

  1. Demolition

    We take out tiles, old parquet and loose plaster, knock down the walls you're moving and clear the rubbish.

  2. Electrics

    We put in new wiring, from the consumer unit to every socket and switch.

  3. New pipes

    We fit new water and drain pipes, from the riser to every point.

  4. Walls and ceilings

    We plaster and fill, and where a wall is too far out we line it with plasterboard on a frame.

  5. Screed

    We pour new screed so laminate or tiles lie flat.

  6. Finishing

    We paint, lay tiles and laminate, and fit the bathroom, sockets and lights.

What it costs

Full renovation, labourfrom €150/m²
Wall demolitionfrom 80 lei/m²
Electrical pointfrom 150 lei/point
Water and drain pointfrom 200 lei/point

The price goes up if walls, floors and pipes are in poor shape, if there is a lot to demolish or walls to move, or if you choose expensive finishes or small tiles. Furniture, interior doors, appliances and decor are not included in any renovation type. The visit, measuring and estimate are free.

All prices

Questions people ask

How long does a full renovation take?

Usually 8-12 weeks. The exact time goes in the contract.

Do the building's risers need replacing too?

Shared risers belong to the owners' association. We replace the pipes in the flat, from the riser on.

Can a full renovation be done in parts?

Yes, you can start with the bathroom and kitchen and do the rooms later.

What makes the price go up?

A lot of demolition, badly crooked walls, moved walls and expensive finishes. They all appear on their own lines in the estimate.

We'll come and see what's in the walls

We check the wiring, pipes and walls, then send an estimate with demolition on separate lines.